Skip to content

Realistic Timeline — What Happens When

Most first-time business owners underestimate the timeline by 50–100%. This page lays out the realistic schedules for three common scenarios so you can plan backwards from your target opening day.


When you see…It means…
Critical pathThe sequence of tasks that determines the minimum project length. A delay on the critical path = a delay to opening day.
FloatSlack time on tasks not on the critical path. Use it for scheduling flexibility.
Lead timeHow long an external item takes from order to delivery (kitchen hood, ABC permit, etc.).
CO (Certificate of Occupancy)The city document permitting you to operate. The doorway to opening day.
TI (Tenant Improvement) allowanceMoney the landlord contributes toward build-out — negotiated in the lease.

You’re moving into a space that was already used for the same kind of business as yours. Maybe a retail shop with new fixtures, paint, signage. No structural work, no plumbing changes, no use change.

WeekMilestoneOn critical path?Notes
0Sign lease
0–1Confirm Change of Tenant requirements with cityFree phone call to 910-433-1707
1–2Submit Change of Tenant application via IDTplans
2–4City review (typically 2–4 weeks for tenant change)
1–3Order signage, fixtures (parallel with city review)
1–2Apply for sign permit if changing signsSign permit ~3–5 business days
1–4Cosmetic work (paint, install fixtures)Can run in parallel with city review
4–5Final inspection
5Receive new Certificate of Occupancy
5–6Open
6+Hire/train staff if needed; soft launch

Realistic: 6–10 weeks lease-to-opening. Add 1–2 weeks for surprises (sign approval delays in Historic District, fixture shipping issues).


You’re moving into a space that needs interior walls built or removed, new finishes, maybe new electrical for your fixtures, but no kitchen and no change of use. Example: bookstore moving into a former clothing store.

WeekMilestoneCritical path?Notes
0Sign LOI / lease
0–2Hire architect or designer; verify GC license at nclbgc.orgSee Hiring a Build-Out Contractor
1–4Architect produces drawingsCosmetic plans: 1–2 weeks; full layout: 3–4 weeks
4–6Submit Change of Tenant + permit applications
6–10City plan review4–8 weeks typical for moderate scope
10–12Address review comments, resubmitUsually 1–2 cycles
12Permits issued
12–20Construction (4–8 weeks for interior build-out)
4–18Order long-lead items in parallel: signage, custom fixturesStart ordering during plan review, not construction
18–20Rough-in inspectionsElectrical, framing
20Final inspections
20–22Receive Certificate of Occupancy
16–22Hire staff, set up POS, marketingParallel work in late stages
22Open

Realistic: 5–6 months lease-to-opening. Historic District adds 2–4 weeks for COA review on any visible exterior changes.


You’re converting a space (often retail or office) into a restaurant with full kitchen, dining seating, and alcohol service. This is the most complex downtown scenario and the one most often miscalculated.

WeekMilestoneCritical path?Notes
0Sign LOI / lease
0–2Pre-submittal feasibility call to Development ServicesCritical — confirm what change-of-use will trigger before signing
2–4Hire architect with restaurant experience; vet GCs
2–4PWC service capacity review (3-phase power, water, sewer)Can take 4–8 weeks just for confirmation
4–10Architectural drawings + MEP engineerFull restaurant: 6–8 weeks
4–6Order kitchen hood (10–14 week lead time)Long lead — order before plans are even approved
4–6Order kitchen equipment (8–12 week lead time on some items)
10–14Submit Change of Use application + permits
14–22City plan review (multi-discipline: building, fire, plumbing)6–10 weeks for full restaurant scope
18–24Address review comments, resubmitOften 2–3 cycles for restaurants
24All permits issued
24–40Construction (8–16 weeks)
24–36Sub schedule: framing → MEP rough → drywall → finishes → equipment
36–40Hood install + fire suppression + grease trap inspections
38–42Health Department plan review and pre-opening inspectionCumberland County Health, 910-433-3600
40–42Final building inspections
42Certificate of Occupancy issued
42NOW apply for ABC alcohol permitCannot apply until CO; ABC takes 30–60 days
42–50ABC review and approval
38–50Hire kitchen staff, train, do soft openingsParallel work
50–52Grand opening with alcohol service

Realistic: 10–12 months lease-to-opening for a full restaurant with alcohol. Push out to 12–14 months if the building has historic-district status, sprinkler retrofit, structural upgrades, or PWC service capacity issues.


The reason these timelines stack up is that critical-path items can’t be parallelized. Here’s the chain for a full restaurant:

Sign Lease
Pre-submittal call (1 day)
Architect/MEP drawings (6–8 weeks)
Submit permit application
Plan review (6–10 weeks, often 2–3 cycles)
Permits issued
Construction (8–16 weeks)
Final inspections
Certificate of Occupancy
├──→ Health Department final inspection
├──→ Fire Marshal final
└──→ ABC permit application (30–60 days)
Open with alcohol

What you can run in parallel (i.e., what’s not on the critical path and gives you “float”):

  • Long-lead equipment orders (start during plan review, not construction)
  • Sign permit application (can run alongside main permits)
  • Hiring and training staff (start mid-construction)
  • Marketing, branding, website, social media (anytime)
  • POS system setup (anytime)
  • Insurance procurement (before opening, not blocking)

Lessons from owners who missed their target dates:

SurpriseHow long it adds
Plan review comments require redesign4–8 weeks per cycle, sometimes 2–3 cycles
Kitchen hood lead time10–14 weeks (most common construction delay)
Grease trap or PWC service upsizing4–12 weeks
Sprinkler retrofit triggered by Change of Use6–12 weeks design + install
Historic Resources Commission review30+ days (HRC meets monthly — miss the deadline, wait a month)
GC discovers hidden conditions during demoVariable — wood rot, asbestos, lead paint, electrical
ABC application backlogCan extend the standard 30–60 days
Health Department comment letter2–4 weeks
Holiday season (Thanksgiving through New Year)Plan reviews and inspections slow during city holidays

Can I open earlier by working with a “permit expediter”? A reputable expediter can shave a few weeks off plan review by submitting clean packages and following up with reviewers. They cannot circumvent statutory review periods or skip steps. Expect to pay $2,000–$10,000 for expediting services, often money well-spent on a complex project.

My landlord says they can give me a CO from when the previous tenant occupied. Is that good enough? No. A CO is specific to the use that was approved at the time it was issued. Your new use needs a new CO. If a landlord tells you otherwise, get it in writing — and then verify with Development Services. The landlord may be honestly mistaken.

What’s the absolute earliest I can apply for an ABC permit? The day your Certificate of Occupancy is issued. ABC typically requires the CO and a copy of your fully executed lease as part of the application. Some preliminary paperwork (entity formation, background checks) can be prepared in advance to speed things up once CO arrives.

Should I sign a lease that starts before construction begins? Common practice is a “free rent period” (60–120 days) at lease start to give time for build-out before paying rent. Negotiate this. For a complex restaurant build-out, free-rent periods of 6+ months are not unreasonable. Without it, you’re paying rent on a space you can’t occupy.

Can I shorten the timeline by skipping the architect for cost reasons? For anything beyond cosmetic work, NC requires sealed drawings (architect or PE) for most non-trivial commercial projects. Skipping the architect usually means the city kicks the application back, costing more time than the architect’s fee would have. The right question is “which architect” — get one with restaurant or commercial-build-out experience.

What if I just want to “soft open” before I have everything done? You cannot legally operate without a Certificate of Occupancy. “Soft open” means inviting friends and family for a private event in a not-yet-permitted space, which is a code violation and an insurance disaster waiting to happen. Wait for CO.


NeedContact
Pre-submittal feasibility (does my space work for my use?)Development Services — 910-433-1707
PWC service capacity reviewPWC — 910-483-1382
Health Department restaurant pre-openingCumberland County Health — 910-433-3600
ABC alcohol permitsNC ABC Commission — 919-779-0700
Free 1:1 timeline planningFTCC Small Business Center — 910-678-8400
Downtown business advisorDowntown Development — 910-433-1599

See also: